The Workhouse
The Workhouse
Location: Enniskillen
Duration: 18 Months
Contractor: QMAC
M + E Consultant: Semple & McKillop
Description
This restoration endeavor involved both the enhancement of the building into a modern centre and the careful preservation of its historical significance.
The ground floor now serves as a versatile area for exhibitions, reminiscence activities, and displays. Meanwhile, the first floor has been transformed into a cutting-edge hub for fostering business innovation and entrepreneurship.
Work Carried Out
The scope of the contract works comprised:
- Low Voltage switchgear
- New containment infrastructure (cable tray/basket/trunking/galvanised conduit)
- General purpose lighting installation
- Data Cabling Installation
- Lighting Installation
- General purpose power and fixed power installation
- Structured cabling/data installation
- Fire alarm Installation
- Disabled refuge / disabled alarms installation
- Intruder alarm installation
- Access control installation
- CCTV installation
- Lightning protection installation
- Electrical works associated with mechanical services